Loomsight
Multifabric Pakistan · Buying office
Inspection Report
PO-1026 · 500 GSM hand towels
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1026
Shipped – all stages passed
LateShipped
Summary
- Buyer
- Harbor & Pine (US)
- Mill
- Indus Terry WorksKarachi, Sindh
- Quantity
- 11,600 pcs
- Ex-factory
- 25 Aug 2026 (actual)
- ETD
- 2 Sep 2026 (actual)
- Current stage
- Shipped
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | 25 Jun 2026 | Ayesha Khan | Pass |
| Dye & Colour Testing | 6 Jul 2026 | Ayesha Khan | Pass |
| DUPRO (mid-production audit) | 1 Aug 2026 | Bilal Ahmed | Pass |
| Final AQL Inspection | 23 Aug 2026 | Hamza Iqbal | Pass |
| Packing & Shipment | 25 Aug 2026 | Sana Malik | Pass |
Final AQL working (ISO 2859-1, Level II)
AQL working: Lot 11,600 → sample 315 → majors 11 (≤14) → minors 12 (≤21) → ACCEPT
Major defects at AQL 2.5 (Ac 14 / Re 15); minor defects at AQL 4.0 (Ac 21 / Re 22). Reject when either count reaches its Re number.
Defects found (DUPRO + final AQL)
| D01 | Hole | major | 1 |
|---|---|---|---|
| D02 | Stain | major | 2 |
| D03 | Shade variation | major | 3 |
| D04 | Broken stitch | major | 6 |
| D06 | Slub | minor | 2 |
| D07 | Loose thread | minor | 8 |
| D10 | Soiling | minor | 4 |
Key readings
Yarn & Weave Check
- Yarn count16.3 Ne
- Thread count64 TC
- Fabric weight612 GSM
- Tensile strength (warp)449 N
Dye & Colour Testing
- Shade standardOptic White 988
- Shade match ΔE (CMC 2:1)0.30
- Colour fastness to washing4
- Rubbing fastness (dry)4
- Rubbing fastness (wet)4
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 12 Jun | 14 Jun | 2 days late |
| Yarn & weave check | 26 Jun | 25 Jun | 1 day early |
| Dyeing & lab dip approval | 8 Jul | 6 Jul | 2 days early |
| Cutting | 20 Jul | 19 Jul | 1 day early |
| DUPRO | 1 Aug | 1 Aug | On time |
| Final AQL | 17 Aug | 23 Aug | 6 days late |
| Ex-factory | 22 Aug | 25 Aug | 3 days late |
| ETD (vessel departs) | 29 Aug | 2 Sep | 4 days late |
Corrective actions (CAPA) · 0 open
CAPA-1026-aql· Final AQL
CAPA closed- Open
- In progress
- Re-inspected
- Closed
- Issue
- Final AQL REJECT: wrong care labels and soiling found in sample.
- Corrective action
- Re-label affected cartons, clean or replace soiled pieces, re-offer full lot.
Opened 17 Aug 2026Due 24 Aug 2026Re-inspection passed 23 Aug 2026Closed 24 Aug 2026
- Root cause (internal)
- Label roll from another PO loaded on one line; packing area not cleaned between orders.
- Owner (internal)
- Imran Shah (dye house manager)
- Internal notes
- Verified on re-inspection. Mill agreed to add check to its in-line SOP.
Photos
Yarn & Weave: Fabric on inspection frame Yarn & Weave: GSM cutter sample Dye & Colour: D65 light box vs lab dip Dye & Colour: Grey scale assessment Dye & Colour: Crockmeter rub test DUPRO: Measurement check on table DUPRO: Sewing line in progress Final AQL: Random sample pull
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Harbor & Pine)
Date: ____________