Inspection Report
PO-1027 · Printed kitchen towels
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1027
Shipped – all stages passed
LateShipped
Summary
- Buyer
- Casa Linea (ES)
- Mill
- Ravi Home FashionsLahore, Punjab
- Quantity
- 8,200 pcs
- Ex-factory
- 16 Sep 2026 (actual)
- ETD
- 20 Sep 2026 (actual)
- Current stage
- Shipped
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | 2 Jul 2026 | Ayesha Khan | Pass |
| Dye & Colour Testing | 13 Jul 2026 | Usman Tariq | Pass |
| DUPRO (mid-production audit) | 7 Aug 2026 | Sana Malik | Pass |
| Final AQL Inspection | 14 Sep 2026 | Sana Malik | Pass |
| Packing & Shipment | 16 Sep 2026 | Sana Malik | Pass |
Final AQL working (ISO 2859-1, Level II)
AQL working: Lot 8,200 → sample 200 → majors 7 (≤10) → minors 7 (≤14) → ACCEPT
Major defects at AQL 2.5 (Ac 10 / Re 11); minor defects at AQL 4.0 (Ac 14 / Re 15). Reject when either count reaches its Re number.
Defects found (DUPRO + final AQL)
| D01 | Hole | major | 2 |
|---|---|---|---|
| D05 | Measurement out of tolerance | major | 1 |
| D06 | Slub | minor | 2 |
| D07 | Loose thread | minor | 4 |
| D08 | Misprint | major | 6 |
| D09 | Wrong label | major | 1 |
| D10 | Soiling | minor | 5 |
Key readings
Yarn & Weave Check
- Yarn count20.4 Ne
- Thread count121 TC
- Fabric weight223 GSM
- Tensile strength (warp)474 N
Dye & Colour Testing
- Shade standardTerracotta 719
- Shade match ΔE (CMC 2:1)0.43
- Colour fastness to washing5
- Rubbing fastness (dry)5
- Rubbing fastness (wet)3
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 19 Jun | 22 Jun | 3 days late |
| Yarn & weave check | 3 Jul | 2 Jul | 1 day early |
| Dyeing & lab dip approval | 15 Jul | 13 Jul | 2 days early |
| Cutting | 27 Jul | 27 Jul | On time |
| DUPRO | 8 Aug | 7 Aug | 1 day early |
| Final AQL | 24 Aug | 14 Sep | 21 days late |
| Ex-factory | 29 Aug | 16 Sep | 18 days late |
| ETD (vessel departs) | 5 Sep | 20 Sep | 15 days late |
Corrective actions (CAPA) · 0 open
CAPA-1027-aql· Final AQL
CAPA closed- Open
- In progress
- Re-inspected
- Closed
- Issue
- Final AQL REJECT: wrong care labels and soiling found in sample.
- Corrective action
- Re-label affected cartons, clean or replace soiled pieces, re-offer full lot.
Opened 2 Sep 2026Due 9 Sep 2026Re-inspection passed 14 Sep 2026Closed 15 Sep 2026
- Root cause (internal)
- Label roll from another PO loaded on one line; packing area not cleaned between orders.
- Owner (internal)
- Kashif Mehmood (production head)
- Internal notes
- Verified on re-inspection. Mill agreed to add check to its in-line SOP.
Photos
Yarn & Weave: Fabric on inspection frame Yarn & Weave: GSM cutter sample Yarn & Weave: Pick glass thread count Dye & Colour: D65 light box vs lab dip Dye & Colour: Grey scale assessment Dye & Colour: Crockmeter rub test DUPRO: Measurement check on table DUPRO: Sewing line in progress
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Casa Linea)
Date: ____________