Printed kitchen towels
QC progress
Only Multifabric sees this panel.
Planned vs actual dates for each production milestone.
Fabric booking
5 days late
Yarn & weave check
2 days early
Dyeing & lab dip approval
14 days late
Cutting
2 days early
DUPRO
2 days early
Final AQL
On time
Ex-factory
2 days late
ETD (vessel departs)
1 day early
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 12 Jul 2026 | 17 Jul 2026 | 5 days late |
| Yarn & weave check | 26 Jul 2026 | 24 Jul 2026 | 2 days early |
| Dyeing & lab dip approval | 7 Aug 2026 | 21 Aug 2026 | 14 days late |
| Cutting | 19 Aug 2026 | 17 Aug 2026 | 2 days early |
| DUPRO | 31 Aug 2026 | 29 Aug 2026 | 2 days early |
| Final AQL | 16 Sep 2026 | 16 Sep 2026 | On time |
| Ex-factory | 21 Sep 2026 | 23 Sep 2026 | 2 days late |
| ETD (vessel departs) | 28 Sep 2026 | 27 Sep 2026 | 1 day early |
Stage 1 of 5
Greige fabric checked against the approved construction.
Yarn count
Target 20 Ne ±3%
20 Ne
Thread count
Target 120 TC ±3%
121 TC
Fabric weight
Target 220 GSM ±5%
219 GSM
Tensile strength (warp)
Target ≥ 450 N
502 N
Process notes
Air-jet looms at reduced RPM for this construction. Greige rolls 4 and 9 checked on the frame.
Stage 2 of 5
Bulk shade and fastness tests against the approved lab dip.
Shade standard
Target Dusty Rose 708
Dusty Rose 708
Shade match ΔE (CMC 2:1)
Target ≤ 1.0
0.49
Colour fastness to washing
Target Grade ≥ 4
4
Rubbing fastness (dry)
Target Grade ≥ 4
4
Rubbing fastness (wet)
Target Grade ≥ 3
3
CAPA-1031-dye
CAPA closedOpened 10 Aug 2026Due 17 Aug 2026Re-inspection passed 21 Aug 2026Closed 22 Aug 2026
Process notes
Reactive dyes, cold pad batch 18 h. Soaping temperature verified at 95 °C.
Stage 3 of 5
During-production inspection of measurements, weights and workmanship.
Production complete
63%
Size / measurement checks
Target ≥ 95% in tolerance
29/30 (96.7%)
Weight checks
Target ≥ 95% in tolerance
20/20 (100%)
Workmanship defects
Target Majors ≤ 5% of sample
2 major · 4 minor in 80 pcs
| D01 | Hole | major | 1 |
|---|---|---|---|
| D06 | Slub | minor | 2 |
| D07 | Loose thread | minor | 1 |
| D08 | Misprint | major | 1 |
| D10 | Soiling | minor | 1 |
Process notes
Line 4 and 5 running this style; line 5 operators newer. Hemming folder replaced mid-shift.
Stage 4 of 5
ISO 2859-1, General Level II, single sampling. Major AQL 2.5, minor AQL 4.0.
Lot size
10,000
Sample size (Level II)
200
Major defects (AQL 2.5)
Target Ac 10 / Re 11
2
Minor defects (AQL 4.0)
Target Ac 14 / Re 15
6
AQL result
Target ACCEPT
ACCEPT
AQL working: Lot 10,000 → sample 200 → majors 2 (≤10) → minors 6 (≤14) → ACCEPT
| D02 | Stain | major | 1 |
|---|---|---|---|
| D07 | Loose thread | minor | 5 |
| D08 | Misprint | major | 1 |
| D10 | Soiling | minor | 1 |
Process notes
Lot presented in finishing hall. Cartons drawn from all pallets; trimming table under-staffed this week.
Stage 5 of 5
Carton, label and shipping-mark verification before loading.
Carton count
417
Labels & shipping marks
Target Checked
Checked
Ship date
27 Sep 2026
Process notes
Pallets wrapped; barcode scans OK on 10% of cartons.