Loomsight
Multifabric Pakistan · Buying office
Inspection Report
PO-1037 · Waffle kitchen towels
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1037
In production – no open failures
On timeQC on track
Summary
- Buyer
- Harbor & Pine (US)
- Mill
- Indus Terry WorksKarachi, Sindh
- Quantity
- 9,000 pcs
- Ex-factory
- 1 Jan 2027 (planned)
- ETD
- 8 Jan 2027 (planned)
- Current stage
- Yarn & Weave
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | — | — | Pending |
| Dye & Colour Testing | — | — | Pending |
| DUPRO (mid-production audit) | — | — | Pending |
| Final AQL Inspection | — | — | Pending |
| Packing & Shipment | — | — | Pending |
Final AQL working (ISO 2859-1, Level II)
Final AQL not yet performed.
Defects found (DUPRO + final AQL)
No defects logged.
Key readings
Yarn & Weave Check
- Yarn count—
- Thread count—
- Fabric weight—
- Tensile strength (warp)—
Dye & Colour Testing
- Shade standard—
- Shade match ΔE (CMC 2:1)—
- Colour fastness to washing—
- Rubbing fastness (dry)—
- Rubbing fastness (wet)—
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 22 Oct | — | Due 22 Oct |
| Yarn & weave check | 5 Nov | — | Due 5 Nov |
| Dyeing & lab dip approval | 17 Nov | — | Due 17 Nov |
| Cutting | 29 Nov | — | Due 29 Nov |
| DUPRO | 11 Dec | — | Due 11 Dec |
| Final AQL | 27 Dec | — | Due 27 Dec |
| Ex-factory | 1 Jan | — | Due 1 Jan |
| ETD (vessel departs) | 8 Jan | — | Due 8 Jan |
Corrective actions (CAPA) · 0 open
No corrective actions were needed on this order.
Photos
Photo pending Photo pending
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Harbor & Pine)
Date: ____________