Loomsight
Multifabric Pakistan · Buying office
Inspection Report
PO-1038 · Fitted sheets, king
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1038
In production – no open failures
At riskQC on track
Summary
- Buyer
- Northbrook Home (UK)
- Mill
- Ravi Home FashionsLahore, Punjab
- Quantity
- 1,000 pcs
- Ex-factory
- 11 Nov 2026 (planned)
- ETD
- 18 Nov 2026 (planned)
- Current stage
- DUPRO
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | 14 Sep 2026 | Bilal Ahmed | Pass |
| Dye & Colour Testing | 8 Oct 2026 | Hamza Iqbal | Pass |
| DUPRO (mid-production audit) | — | — | Pending |
| Final AQL Inspection | — | — | Pending |
| Packing & Shipment | — | — | Pending |
Final AQL working (ISO 2859-1, Level II)
Final AQL not yet performed.
Defects found (DUPRO + final AQL)
No defects logged.
Key readings
Yarn & Weave Check
- Yarn count19.6 Ne
- Thread count119 TC
- Fabric weight228 GSM
- Tensile strength (warp)509 N
Dye & Colour Testing
- Shade standardOptic White NB-001
- Shade match ΔE (CMC 2:1)0.64
- Colour fastness to washing4
- Rubbing fastness (dry)4
- Rubbing fastness (wet)3
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 1 Sep | 31 Aug | 1 day early |
| Yarn & weave check | 15 Sep | 14 Sep | 1 day early |
| Dyeing & lab dip approval | 27 Sep | 8 Oct | 11 days late |
| Cutting | 9 Oct | — | 4 days late (open) |
| DUPRO | 21 Oct | — | Due 21 Oct |
| Final AQL | 6 Nov | — | Due 6 Nov |
| Ex-factory | 11 Nov | — | Due 11 Nov |
| ETD (vessel departs) | 18 Nov | — | Due 18 Nov |
Corrective actions (CAPA) · 0 open
CAPA-1038-1· Dye & Colour
CAPA closed- Open
- In progress
- Re-inspected
- Closed
- Issue
- Colour fastness to washing grade 3 (minimum 4).
- Corrective action
- Re-wash with improved soaping and fixing, then re-test fastness on 3 samples.
Opened 22 Sep 2026Due 29 Sep 2026Re-inspection passed 8 Oct 2026Closed 9 Oct 2026
- Root cause (internal)
- Soaping bath temperature dropped below 90 °C on second shift.
- Owner (internal)
- Farah Qureshi (QA manager)
- Internal notes
- Re-test passed at grade 4. Mill added a temperature log to the soaping range.
Photos
Yarn & Weave: Fabric on inspection frame Yarn & Weave: GSM cutter sample Yarn & Weave: Pick glass thread count Dye & Colour: D65 light box vs lab dip Dye & Colour: Grey scale assessment
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Northbrook Home)
Date: ____________