Linen-look cushion covers
QC progress
Only Multifabric sees this panel.
Planned vs actual dates for each production milestone.
Fabric booking
1 day early
Yarn & weave check
1 day early
Dyeing & lab dip approval
22 days late (open)
Cutting
10 days late (open)
DUPRO
Due 15 Oct
Final AQL
Due 31 Oct
Ex-factory
Due 5 Nov
ETD (vessel departs)
Due 12 Nov
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 26 Aug 2026 | 25 Aug 2026 | 1 day early |
| Yarn & weave check | 9 Sep 2026 | 8 Sep 2026 | 1 day early |
| Dyeing & lab dip approval | 21 Sep 2026 | — | 22 days late (open) |
| Cutting | 3 Oct 2026 | — | 10 days late (open) |
| DUPRO | 15 Oct 2026 | — | Due 15 Oct |
| Final AQL | 31 Oct 2026 | — | Due 31 Oct |
| Ex-factory | 5 Nov 2026 | — | Due 5 Nov |
| ETD (vessel departs) | 12 Nov 2026 | — | Due 12 Nov |
Stage 1 of 5
Greige fabric checked against the approved construction.
Yarn count
Target 20 Ne ±3%
20.2 Ne
Thread count
Target 120 TC ±3%
120 TC
Fabric weight
Target 220 GSM ±5%
215 GSM
Tensile strength (warp)
Target ≥ 450 N
530 N
Process notes
Ring-spun yarn from in-house spinning, lot 7B. Twist checked on 5 cones.
Stage 2 of 5
Bulk shade and fastness tests against the approved lab dip.
Shade standard
—
Shade match ΔE (CMC 2:1)
Target ≤ 1.0
—
Colour fastness to washing
Target Grade ≥ 4
—
Rubbing fastness (dry)
Target Grade ≥ 4
—
Rubbing fastness (wet)
Target Grade ≥ 3
—
Stage 3 of 5
During-production inspection of measurements, weights and workmanship.
Production complete
—
Size / measurement checks
Target ≥ 95% in tolerance
—
Weight checks
Target ≥ 95% in tolerance
—
Workmanship defects
Target Majors ≤ 5% of sample
—
Stage 4 of 5
ISO 2859-1, General Level II, single sampling. Major AQL 2.5, minor AQL 4.0.
Lot size
3,500
Sample size (Level II)
200
Major defects (AQL 2.5)
Target Ac 10 / Re 11
0
Minor defects (AQL 4.0)
Target Ac 14 / Re 15
0
AQL result
Target ACCEPT
ACCEPT
AQL working: Lot 3,500 → sample 200 → majors 0 (≤10) → minors 0 (≤14) → ACCEPT
Stage 5 of 5
Carton, label and shipping-mark verification before loading.
Carton count
—
Labels & shipping marks
Target Checked
Not checked
Ship date
—