New here? Take the 60-second tour.
Buyer view → order timeline → a failed QC check → the CAPA it opens → analytics.
Follow your orders' QC milestones and reports.
Reference date: 13 Oct 2026New here? Take the 60-second tour.
Buyer view → order timeline → a failed QC check → the CAPA it opens → analytics.
Fitted sheets, king
QC progress
Milestone-based visibility. Mill processes stay confidential. You see every inspection result as it is recorded; mill identity and floor notes are shared only where Multifabric has agreed it with the mill.
Planned vs actual dates for each production milestone.
Fabric booking
1 day early
Yarn & weave check
1 day early
Dyeing & lab dip approval
11 days late
Cutting
4 days late (open)
DUPRO
Due 21 Oct
Final AQL
Due 6 Nov
Ex-factory
Due 11 Nov
ETD (vessel departs)
Due 18 Nov
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 1 Sep 2026 | 31 Aug 2026 | 1 day early |
| Yarn & weave check | 15 Sep 2026 | 14 Sep 2026 | 1 day early |
| Dyeing & lab dip approval | 27 Sep 2026 | 8 Oct 2026 | 11 days late |
| Cutting | 9 Oct 2026 | — | 4 days late (open) |
| DUPRO | 21 Oct 2026 | — | Due 21 Oct |
| Final AQL | 6 Nov 2026 | — | Due 6 Nov |
| Ex-factory | 11 Nov 2026 | — | Due 11 Nov |
| ETD (vessel departs) | 18 Nov 2026 | — | Due 18 Nov |
Stage 1 of 5
Greige fabric checked against the approved construction.
Yarn count
Target 20 Ne ±3%
19.6 Ne
Thread count
Target 120 TC ±3%
119 TC
Fabric weight
Target 220 GSM ±5%
228 GSM
Tensile strength (warp)
Target ≥ 450 N
509 N
Mill process notes stay confidential.
Stage 2 of 5
Bulk shade and fastness tests against the approved lab dip.
Shade standard
Target Optic White NB-001
Optic White NB-001
Shade match ΔE (CMC 2:1)
Target ≤ 1.0
0.64
Colour fastness to washing
Target Grade ≥ 4
4
Rubbing fastness (dry)
Target Grade ≥ 4
4
Rubbing fastness (wet)
Target Grade ≥ 3
3
CAPA-1038-1
CAPA closedOpened 22 Sep 2026Due 29 Sep 2026Re-inspection passed 8 Oct 2026Closed 9 Oct 2026
Mill process notes stay confidential.
Stage 3 of 5
During-production inspection of measurements, weights and workmanship.
Production complete
—
Size / measurement checks
Target ≥ 95% in tolerance
—
Weight checks
Target ≥ 95% in tolerance
—
Workmanship defects
Target Majors ≤ 5% of sample
—
Stage 4 of 5
ISO 2859-1, General Level II, single sampling. Major AQL 2.5, minor AQL 4.0.
Lot size
1,000
Sample size (Level II)
80
Major defects (AQL 2.5)
Target Ac 5 / Re 6
0
Minor defects (AQL 4.0)
Target Ac 7 / Re 8
0
AQL result
Target ACCEPT
ACCEPT
AQL working: Lot 1,000 → sample 80 → majors 0 (≤5) → minors 0 (≤7) → ACCEPT
Stage 5 of 5
Carton, label and shipping-mark verification before loading.
Carton count
—
Labels & shipping marks
Target Checked
Not checked
Ship date
—