Loomsight
Multifabric Pakistan · Buying office
Inspection Report
PO-1034 · 600 GSM bath towels
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1034
In production – no open failures
At riskQC on track
Summary
- Buyer
- Harbor & Pine (US)
- Mill
- Indus Terry WorksKarachi, Sindh
- Quantity
- 12,000 pcs
- Ex-factory
- 15 Oct 2026 (planned)
- ETD
- 22 Oct 2026 (planned)
- Current stage
- Packing
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | 18 Aug 2026 | Hamza Iqbal | Pass |
| Dye & Colour Testing | 30 Aug 2026 | Sana Malik | Pass |
| DUPRO (mid-production audit) | 23 Sep 2026 | Ayesha Khan | Pass |
| Final AQL Inspection | 12 Oct 2026 | Bilal Ahmed | Pass |
| Packing & Shipment | — | — | Pending |
Final AQL working (ISO 2859-1, Level II)
AQL working: Lot 12,000 → sample 315 → majors 7 (≤14) → minors 19 (≤21) → ACCEPT
Major defects at AQL 2.5 (Ac 14 / Re 15); minor defects at AQL 4.0 (Ac 21 / Re 22). Reject when either count reaches its Re number.
Defects found (DUPRO + final AQL)
| D02 | Stain | major | 2 |
|---|---|---|---|
| D03 | Shade variation | major | 1 |
| D04 | Broken stitch | major | 3 |
| D05 | Measurement out of tolerance | major | 1 |
| D06 | Slub | minor | 2 |
| D07 | Loose thread | minor | 13 |
| D09 | Wrong label | major | 1 |
| D10 | Soiling | minor | 6 |
Key readings
Yarn & Weave Check
- Yarn count15.9 Ne
- Thread count64 TC
- Fabric weight582 GSM
- Tensile strength (warp)458 N
Dye & Colour Testing
- Shade standardHarbor Navy HP-220
- Shade match ΔE (CMC 2:1)0.35
- Colour fastness to washing5
- Rubbing fastness (dry)4
- Rubbing fastness (wet)4
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 5 Aug | 4 Aug | 1 day early |
| Yarn & weave check | 19 Aug | 18 Aug | 1 day early |
| Dyeing & lab dip approval | 31 Aug | 30 Aug | 1 day early |
| Cutting | 12 Sep | 11 Sep | 1 day early |
| DUPRO | 24 Sep | 23 Sep | 1 day early |
| Final AQL | 10 Oct | 12 Oct | 2 days late |
| Ex-factory | 15 Oct | — | Due 15 Oct |
| ETD (vessel departs) | 22 Oct | — | Due 22 Oct |
Corrective actions (CAPA) · 0 open
No corrective actions were needed on this order.
Photos
Yarn & Weave: Fabric on inspection frame Yarn & Weave: GSM cutter sample Dye & Colour: D65 light box vs lab dip Dye & Colour: Grey scale assessment Dye & Colour: Crockmeter rub test DUPRO: Measurement check on table DUPRO: Sewing line in progress Final AQL: Random sample pull
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Harbor & Pine)
Date: ____________