PO-1041 · Crew-neck T-shirts
- Report date
- 13 Oct 2026
- Reference
- MF-QR-1041
In production – no open failures
At riskQC on track
Summary
- Buyer
- Lindenhof Wohnen (DE)
- Mill
- Sutlej KnitwearFaisalabad, Punjab
- Quantity
- 8,000 pcs
- Ex-factory
- 26 Oct 2026 (planned)
- ETD
- 2 Nov 2026 (planned)
- Current stage
- Final AQL
| Stage | Date | Inspector | Result |
|---|---|---|---|
| Yarn & Weave Check | 29 Aug 2026 | Usman Tariq | Pass |
| Dye & Colour Testing | 10 Sep 2026 | Bilal Ahmed | Pass |
| DUPRO (mid-production audit) | 9 Oct 2026 | Sana Malik | Pass |
| Final AQL Inspection | — | — | Pending |
| Packing & Shipment | — | — | Pending |
Final AQL working (ISO 2859-1, Level II)
Final AQL not yet performed.
Defects found (DUPRO + final AQL)
| D07 | Loose thread | minor | 1 |
|---|---|---|---|
| D09 | Wrong label | major | 1 |
| D10 | Soiling | minor | 1 |
Key readings
Yarn & Weave Check
- Yarn count29.9 Ne
- Thread count55 TC
- Fabric weight182 GSM
- Tensile strength (warp)292 N
Dye & Colour Testing
- Shade standardHeather Grey KN-08
- Shade match ΔE (CMC 2:1)0.89
- Colour fastness to washing4
- Rubbing fastness (dry)5
- Rubbing fastness (wet)4
Time & Action status
| Milestone | Planned | Actual | Status |
|---|---|---|---|
| Fabric booking | 16 Aug | 15 Aug | 1 day early |
| Yarn & weave check | 30 Aug | 29 Aug | 1 day early |
| Dyeing & lab dip approval | 11 Sep | 10 Sep | 1 day early |
| Cutting | 23 Sep | 22 Sep | 1 day early |
| DUPRO | 5 Oct | 9 Oct | 4 days late |
| Final AQL | 21 Oct | — | Due 21 Oct |
| Ex-factory | 26 Oct | — | Due 26 Oct |
| ETD (vessel departs) | 2 Nov | — | Due 2 Nov |
Corrective actions (CAPA) · 1 open
CAPA-1041-1· DUPRO
CAPA re-inspected- Open
- In progress
- Re-inspected
- Closed
- Issue
- Chest width out of tolerance (±1 cm) on 4 of 30 pieces measured; broken stitches at shoulder seam.
- Corrective action
- Cutting pattern corrected and re-graded. First 50 pieces per line re-measured; affected bundles segregated.
Opened 2 Oct 2026Due 9 Oct 2026Re-inspection passed 9 Oct 2026
- Root cause (internal)
- Shrinkage allowance not updated after the fabric lot changed.
- Owner (internal)
- Kashif Mehmood (production head)
- Internal notes
- Re-inspection clean. Close once the buyer confirms the revised size set.
Photos
Yarn & Weave: Fabric on inspection frame Yarn & Weave: GSM cutter sample Yarn & Weave: Pick glass thread count Dye & Colour: D65 light box vs lab dip Dye & Colour: Grey scale assessment Dye & Colour: Crockmeter rub test DUPRO: Measurement check on table DUPRO: Sewing line in progress
Inspected by (Multifabric QC)
Date: ____________
Approved by (QC Manager)
Date: ____________
Acknowledged by (Lindenhof Wohnen)
Date: ____________